Customize Consent Preferences

We use cookies to help you navigate efficiently and perform certain functions. You will find detailed information about all cookies under each consent category below.

The cookies that are categorised as "Necessary" are stored on your browser as they are essential for enabling the basic functionalities of the site.... 

Always Active

Necessary cookies are required to enable the basic features of this site, such as providing secure log-in or adjusting your consent preferences. These cookies do not store any personally identifiable data.

Functional cookies help perform certain functionalities like sharing the content of the website on social media platforms, collecting feedback, and other third-party features.

No cookies to display.

Analytical cookies are used to understand how visitors interact with the website. These cookies help provide information on metrics such as the number of visitors, bounce rate, traffic source, etc.

Performance cookies are used to understand and analyze the key performance indexes of the website which helps in delivering a better user experience for the visitors.

No cookies to display.

Advertisement cookies are used to provide visitors with customized advertisements based on the pages you visited previously and to analyze the effectiveness of the ad campaigns.

No cookies to display.

Nottingham Train Station Platform Resurfacing

Nottingham Train Station Platform Resurfacing

Nottingham
£300,000
10 Weeks

Platforms 1C and 2 at Nottingham rail station required resurfacing, to bring their cross falls in line with current Network Rail standards. The cross fall towards these platforms’ edges had been identified as too great, making them safety hazards for prams and wheelchair users.

Action

  • Removal of existing paving
  • Replacing with new Marshall Perfecta Paving (approx 650m2)
  • Localised resetting of tactiles to ensure new platform cross falls meets current NR standards
  • Adjustments to existing coper to suit new levels & falls.
  • Installation of new drainage channel and sump units to platforms (approx 100m)



Result

Works completed successfully on time and within budget, to the delight of Network Rail.

Stakeholders

From our earliest involvement we nurtured an inclusive and elaborate approach to managing the works, ensuring all stakeholders views were understood and their expectations managed accordingly and appropriately.
Challenges & Solutions

  • Operational Use Had To Be Maintained – We undertook the works in phases to ensure continuing operational use of both platforms. Coper and Tactile works were carried out during night-time possessions
  • Very Restricted Access – All materials being delivered or removed to work areas were across the tracks during line blocks at night


The Difference We Made

  • Platform safety brought in line with current Network Rail standards, ensuring the continued safety of rail passengers.
  • Platform paving and altering levels brought in line with current Network Rail standards.