Progress Update: Huddersfield Junction Improvement Works
We are pleased to report significant progress on the improvement scheme at one of the busiest junctions in Huddersfield. Recent activity includes:
Works completed in September
Phase 1 & Phase 2
- Completed all kerbing works.
- Constructed traffic island on Lockwood Road.
- Opened the link road 15.09.2025, including new road markings.
- Configured the new traffic lights so the link road junction is fully operational.
- Completed all service diversions works.
New pedestrian routes now put in place.
Phase 3
Completed works to the gate in the school grounds
Phase 4 / 5A
- Commenced site clearance – breaking out existing tarmac, kerbs and channels.
- Started installing gullies and ducting including duct chambers.
- City Fiber diversion works have been completed.
Future works for October:
Phases 4 / 5A
- Continue with site clearance works.
- Continue installing ducting, drainage and kerbs/edgings to footways.
- Install remaining illuminated signs and standard signs.
- Install new street light columns and cabling.
- Footway preparation inc. sub-base and compaction.
- Commence paving works to footways.